π¨ remove 1stβ2nd floor internal staircase and rebuild vault/floor
πͺ plumbing core 2nd floor bedroom bathroom connections, pipe across kitchen, descent into and across ground
π founder move-in
π§Ύ fibre contract
πͺ develop and test bedroom door design
π¨ 6 bedrooms all 2nd floor
πͺ develop and test bed base design
πͺ develop and test inset sliding bathroom door design
πͺ 1 ensuite initially shared
π§Ή strip/repoint/paint vaulting (1st, ground)
πͺ basic kitchen
Preliminary: completion May '27
volunteering / work-exchange begins
πͺ new 1st floor rear windows
π§Ύ buy vehicle
πͺ dining
π¨ 1st shared bathroom 3rd floor
πͺ 1 ensuite
πͺ dorm room and pods 5 on 3rd floor
πͺ develop and test pod design
π¨ swap 1st balcony door and window lower window opening to fit, and blockup old doorway for window
π¨ demolish ground dividing wall possible beam strengthening
πͺ£ insulate and render walls north, east, west
π¨ 2nd floor staircase concrete formwork; demolition of existing
6 bedrooms, 5 pods; adventurous rates -70%
Intial operations: completion June '27
πͺ more kitchen
πͺ install temporary ground floor windows
πͺ workspace
π¨ cave lintel
πͺ terrace
adequate rates -50%
Full capacity: unscheduled
all remaining rooms / 3rd floor
πͺ minor roof strengthening and repairs
π¨ partitions, insulation, infra
π¨ 2nd shared bathroom
πͺ new bedrooms 4: 2 plus, 1 plain, 1 petite
πͺ 3rd floor door
πͺ full kitchen
πͺ front garden
launch rates -35%
Finishing: unscheduled
π¨ shed & laundry
π¨ callroom
πͺ replace 2nd floor door
πͺ workspace daybeds
πͺ common flooring lounge, kitchen and workspace
πͺ remaining ensuites
Extended operations: unscheduled
providing winter coverage
π¨ seal ground nook
π¨ staircase 2ndβ3rd floor and roof; either temporary single-pane glass or PVC double; either timber frame with insulation and timber cladding or breeze-block
π duvets
πͺ bathroom heating
πͺ room heating
πͺ dining heating
πͺ coworking heating
low season operations begin
Niceties: unscheduled
bonus facilities for extra appeal; deferable
πͺ£ cave repointing and floor
πͺ cave fitout
π¨ 3rd shared bathroom
πͺ atrium roof and fitout
π¨ sauna
π¨ new lintel and window to enlarge and replace (tiny) window in 2nd floor plain bedroom
π¨ rebuild groundβ1st steps
rates begin targetting potential
Miscellaneous tasks
sewing: curtains
sewing: mattress toppers, wool batts and felt, linen covers